National Performance Centre for Curling

Sector: Leisure
Participant: Stirling Council
Location: Stirling
Capital Value: c£2m
Procurement: NEC3
GiFA: c1,385m²
Anticipated Start Date: April 2016
Construction Period: 3 weeks mobilisation, 37 weeks construction
BREEAM Target: N/A

 

Project Description

The project comprises of an extension to The Peak, Stirling's flagship sport and wellbeing centre, to provide a facility to support the development of elite performance curling within Scotland.  The high quality performance environment will provide a dedicated 4 sheet facility that will allow Scotland's top curlers access to championship quality ice throughout the year.

 

Key Appointments

Contractor: Robertson Construction
FM Operator: N/A
Architect: BDP
Civil & Structural Engineer: Dewar Associates
Building Services: DSSR
Principal Designer: Brownriggs
BREEAM Assessor: N/A
hub PM Contact: Wayne Sutherland
Tier 1 Contractor Contact: Stephen Home