CAMHS

Sector: Healthcare
Participant: NHS Tayside
Location:  Dundee
Capital Value:  £5.7m
Completion Date: March 2015
Contract Dates: 13 months
Total Users / Residents:

12 in-patient beds and accommodation for families

Carbon Footprint:

BREEAM Very good

Local Employees:

450 of 643 employed

Replacement Details:

6-bed facility at Dudhope House which is no longer suitable.

Project Information

Forming part of the Arbroath Schools Project, the new-build school provides modern learning spaces fit to meet the demands of the school curriculum for 335 pupils, 72 pre-school children and 35 staff members.

Built on the playing fields of the existing school, the former facility remained operational throughout construction. Once pupils and staff transferred to the new building, we demolished the old school and carried out ground levelling works before completing the sports pitch, carparking and landscaping.

Across its 3,018 m2, the building comprises a steel frame and structural timber inner leaf, with external glazing and cladding.

Community Involvement

Close engagement with community stakeholders during preconstruction to ensure access to existing facilities was maintained during construction, and gather opinions on future facilities.

Key Appointments

Principle Contractor: BAM Construction
Architect: Gauldie Wright & Partners
Civil & Structural Engineer:  Goodsons
M&E Engineer: FES
Project Lead: hub East Central Scotland

 