Durieshill

Get social and share
Sector: Education
Participant: Stirling Council 
Location: Durieshill, Stirling
Capital Value: £21.2M
Procurement: D&B
GiFA: Approx 3,000m2 
Anticipated Start Date: July 2026
Construction Period: 68 weeks
Energy Target: Passivhaus 

Project Description

A new village is being developed by Barratt Groups at Durieshill, Stirling that will see the creation of more than 3,000 new houses over the next 30 years, with a mix of tenures including private, social and private rented housing, which will attract first-time buyers and families. 

As part of the overall development, Stirling Council have identified the community and education facilities that will be required over a number of phases, as the village population grows. These facilities include: 

  • Primary School 1 (Phase 1) – 10 classrooms
  • Primary School 1 (Phase 2) – 4 classroom extension
  • Nursery / Early Years Facility
  • ASN Facility

This commission will focus on the design and construction of a new Primary School 1 (Phase 1) designed to the Passivhaus Standard on a site within the new housing development. A 10-classroom primary school for 292 pupils will be provided, including associated external play & teaching spaces and car parking. 

Key Appointments

Contractor: Robertson Construction Central East
FM Operator: N/A
Architect: Architype
Civil & Structural Engineer: Goodson Associates
Building Services: Rybka
Principal Designer: Gardiner & Theobald
Breeam Assessor: N/A
hub Project Manager: Yvonne Roddie
Tier 1 Project Manager: Audrey Gilmour