Kirkcaldy Innovation Growth Hub
| Sector: | Commercial |
| Participant: | Fife Council |
| Location: | Kirkcaldy |
| Capital Value: | £19M |
| Procurement: | DBDA |
| GiFA: | 1,000m2 |
| Anticipated Start Date: | December 2026 |
| Construction Period: | 60 weeks |
| Energy Target: | Building Standards as a minimum |
Project Description
Kirkcaldy Growth Works
The new Growth Works building will provide facilities to support new business start-ups through a variety of different functions including Food & Beverage / Office Space and opportunities for performance and displaying work as well as supporting pop-up events and opportunities for local people to sell locally made produce.
Key Appointments
| Contractor: | BAM Construction |
| FM Operator: | N/A |
| Architect: | AHR |
| Civil & Structural Engineer: | Aecom |
| Building Services: | Rybka |
| Principal Designer: | AHR |
| Sustainability Assessor: | N/A |
| hub Project Manager: | Wayne Sutherland |
| Tier 1 Project Manager: | Paul Gallacher |