NHS Tayside Pharmaceutical Specials Service Project

Sector: Health
Participant: NHS Tayside (lead participant) for NHS Scotland
Location: Dundee
Capital Value: £25m
Procurement: DBFM (Design, Build, Finance and Maintain)
GiFA: c4,000m²
Anticipated Start Date: Jan 2017
Construction Period: 21 Months
BREEAM Target: Very Good

Project Description

The project involves the design and construction of an NHS Manufacturing Unit for the supply of unlicensed medicines to all 14 health board in NHS Scotland.

Key Appointments

Contractor: Robertson Construction
FM Operator: Robertson FM
Architect: Sheppard Robson
Civil & Structural Engineer: Woolgar Hunter
Building Services: Morgan Sindall Professional Services
Principal Designer: Currie & Brown
BREEAM Assessor: Wallace Whittle
Clean Room Specialist: Bouygues
hub Project Manager: Gary Wright
Tier 1 Project Manager: Richard McElfatrick