North Muirton Primary School

Sector: Education
Participant: Perth & Kinross Council
Location: North Muirton, Perth
Capital Value: £18M
Procurement: DBDA
GiFA: 4283 m2
Anticipated Start Date: Nov 2021
Construction Period: Phase 1 PC April 23, Phase 2 PC Nov 23
Breeam Target: N/A Passivhaus Classic Accreditation

Project Description

Combining the existing North Muirton and Balhousie Primary Schools to form a new replacement school to be named Riverside Primary School.  New facility has the capacity for 500nr Primary Pupils, 82nr Nursery Pupils and 16nr ASN Pupils.  New school is on the site of the existing North Muirton Primary which will be demolished upon completion.  Project also includes for associated hard and soft landscaped playground areas.

Key Appointments

Contractor: Robertson Tayside
FM Operator: N/A
Architect: Architype
Civil & Structural Engineer: Goodson
Building Services: Baker Hicks
Principal Designer: Kirk & Marsh
Breeam Assessor: Passivhaus Designer is Architype and Certifier is WARM
hub Project Manager: Craig Fraser
Tier 1 Project Manager: Gerry Hampton